Learn what a project initiation document (PID) includes, how to write one step by step and how it differs from a project charter.
A project initiation document (PID) is the formal document that sets out a project’s purpose, scope, objectives, governance and success criteria before delivery begins. Once approved by the sponsor or project board, it becomes the agreed baseline that every later decision and change is measured against. It gives the project manager, sponsor and stakeholders a shared understanding of what the project is, why it exists and how it will be run. This guide explains what a PID contains, how it differs from a project charter, how to write one step by step and the mistakes that weaken it.
Boost your career with the PRINCE2 7 Foundation Certification, a globally recognised credential for aspiring project managers.
The PID is the main output of the initiation stage. It pulls the early thinking about a project into one approved record that authorises the work to go ahead. It is less a summary than an agreement: the project team commits to delivering a defined scope in a defined way, and the sponsor commits to the resources and decisions needed to make that possible.
In PRINCE2, the abbreviation stands for project initiation documentation, because it is a collection of documents rather than a single file. Many organisations outside PRINCE2 use “project initiation document” for a single consolidated document. Either way, the purpose is the same: one approved reference point for the project.
Without a PID, decisions drift, scope grows without control and accountability is hard to establish. With one, the project board can check at any point whether the project is still delivering what was agreed.
A well-structured PID typically covers:
Scope and assumptions deserve particular care. Many disputes later in a project trace back to an assumption that was never written down. Recording assumptions in the PID, and reviewing them at each stage gate, turns hidden risks into visible ones. Our guide to project deliverables explains how to define what the project will produce in enough detail to baseline it.
The PID turns an approved idea or business case into a governed project. Its most important job is to assign accountability: it names the sponsor, defines the project manager’s authority and sets out how decisions are escalated. When change, conflict or uncertainty arises, the PID is the reference that keeps decisions grounded in what was agreed.
It also supports assurance. Project boards, steering committees and auditors use it to check whether the project is still aligned with its objectives and whether changes were properly approved. For sponsors, understanding what a good PID contains is as important as it is for project managers, and IPM’s Project Sponsor Programme covers the initiation stage from the sponsor’s side.
The two documents serve a similar purpose but come from different traditions.
| Aspect | Project initiation document (PID) | Project charter |
|---|---|---|
| Origin | PRINCE2 and UK public sector practice | PMBOK Guide (Project Management Institute) |
| Purpose | Defines how the project will be directed, managed and controlled | Formally authorises the project and the project manager |
| Level of detail | Detailed: plans, controls and management approaches | Short: purpose, objectives, high-level scope and authority |
| Approved by | Project board or sponsor | Sponsor or initiating organisation |
| Detailed planning | Included or referenced within the PID | Captured separately in the project management plan |
Neither approach is better in every situation. A short charter suits smaller projects and organisations that keep detailed planning elsewhere, while a PID suits environments that expect strong governance and a single approved baseline. Both aim to establish agreement and accountability before execution begins. Our guide to what a project charter is covers charters in more detail.
Learn the project sponsor role and how effective sponsorship drives alignment, decisions, and benefits realisation.
Writing a PID starts well before you open a template. Work through these steps with the sponsor and key stakeholders.
Draft iteratively rather than in one sitting, and build the communication plan alongside the stakeholder analysis. A PID approved without a communication plan is incomplete, however thorough its other sections.
Learn core project management principles and build practical skills to support successful project delivery.
In PRINCE2, the PID is produced during the Initiating a Project process and approved by the project board before the first delivery stage begins. It brings together the business case, the project plan, the project’s organisation and a set of management approaches describing how areas such as risk, quality, change, communication and benefits will be handled. It is then maintained as a living record, updated at stage boundaries and through change control. IPM’s PRINCE2 Foundation course covers the method and its management products in detail.
Under the PMBOK Guide, a project charter and a project management plan together cover similar ground to a PID. In agile environments, initiation is usually lighter, with a product vision, an initial backlog and a team agreement, such as a team charter, playing a similar role. Many organisations now run hybrid projects, keeping a PID-style document for governance and sponsor reporting while the team delivers in iterations. Knowing how initiation adapts across approaches is part of the cross-methodology awareness developed in IPM CPM Level 1.
The business case answers whether the project is worth doing: it sets out the investment, expected benefits and alternatives. The PID answers how the project will be done, turning the approval behind the business case into a governed plan. In PRINCE2, the business case is maintained alongside the PID and reviewed at every stage boundary. If the expected benefits can no longer be realised, the project should be reconsidered, and no PID can rescue a project whose rationale has gone.
The project manager usually writes the PID, drawing on input from the sponsor, subject matter experts, the project team and key stakeholders. The sponsor or project board reviews it and gives formal approval. In PRINCE2, the project board’s approval of the PID is the decision that authorises the project to move from initiation into delivery. Business analysts, finance partners and risk specialists often contribute specific sections, but one person, normally the project manager, should own the document and keep it up to date.
To see how the sections fit together, consider a 200-person office relocation.
| Section | Example content |
|---|---|
| Objective | Move all staff to the new building by 30 June with no more than one working day of disruption per team |
| Scope | In: furniture, IT equipment, network set-up, staff communications. Out: new furniture purchases, changes to the phone system |
| Key assumption | The landlord hands over the new building by 1 May |
| Top risk | Network installation delays, owned by the IT manager |
| Governance | Monthly project board chaired by the operations director; the project manager can approve changes up to £5,000 |
| Success criteria | All staff working from the new site by 30 June and the budget held within 5% |
Each line is specific enough to check later. If the landlord’s handover slips, the board can see immediately which assumption has failed and what it affects.
Templates help ensure nothing is missed, but the value of a PID depends on the quality of the thinking behind it. A template completed without stakeholder input, risk analysis or sponsor sign-off is a form-filling exercise, not a PID.
A project initiation document gives a project its foundations: clear objectives, an agreed scope, named accountability and a baseline for every later decision. Produced well, it lets complex work proceed with confidence. Produced poorly, it creates the conditions for scope creep and missed expectations. Agree the objectives first, record scope and assumptions explicitly, involve stakeholders and secure formal approval, then keep the PID up to date as the project moves through its stages.
A PID establishes an agreed, approved baseline for a project before delivery begins. It records objectives, scope, governance, risks and stakeholder responsibilities, and it authorises the project to move beyond initiation.
The PID is a governance document that sets out why and how the project will be run. The project plan sets out what will be done, in what order, by whom and when. In PRINCE2, the project plan is part of the PID.
A project charter, used in the PMBOK Guide, is a short document that authorises the project and the project manager. A PID, used in PRINCE2, is more detailed and includes the plans, controls and management approaches for the project.
Yes. Approval by the project board or sponsor gives the PID its authority and creates the baseline for change control. Without approval, it is only a draft.
Pure agile teams usually use lighter artefacts such as a product vision and initial backlog. Many organisations running hybrid projects still keep a PID-style document for governance while delivering in iterations.
Highly in-demand across roles, industries, and experience levels
Book Your Free ConsultationJoin IPM Hub, the free community where Project Managers share real challenges and learn from each other.
10% Off your first On-Demand course when you join.
Please activate your account by clicking the verification link we’ve sent to your email.
Once verified, your 10% code will arrive by email.
If the email doesn’t appear soon, please check your spam or junk folder.
We use cookies to ensure you get the best experience of our website. By clicking “Accept”, you consent to our use of cookies.